Quick answer
Under CDM 2015, the client must ensure a Refurbishment or Demolition Survey exists before pre-2000 construction works begin. The principal contractor must brief every operative on the register before they enter site. Asbestos work is one of the top drivers of programme overruns; early surveying almost always saves cost.
CDM roles and asbestos
Client: commission the survey, provide it to the principal designer and principal contractor. Principal designer: coordinate asbestos information into the design. Principal contractor: brief every operative, run permit-to-work, coordinate licensed removal.
Programme integration
Survey at RIBA Stage 3–4. Licensed removal quoted at tender. Removal completes before soft strip. Reassurance and clearance built into programme, not tacked on. Handover register issued at practical completion.
Frequently asked questions
Common questions
Is a Management Survey enough for construction?+
No — CDM works require a Refurbishment or Demolition Survey.
Who signs the reoccupation certificate?+
An independent UKAS-accredited analyst — never the removal contractor.