Refurbishment Surveys
Intrusive survey required before any building work that may disturb the fabric. Protects contractors, dutyholders and the project programme.
Key takeaways
- Domestic kitchen / bathroom: £350–£650
- Small commercial unit (200–500 m²): £700–£1,800
- School or office (1,000–3,000 m²): £2,500–£6,500
- Cat A strip-out (5,000–10,000 m²): £6,500–£15,000+
- Sample analysis: £30–£60 per sample
An independent consultancy view of where refurbishment surveys go wrong and how to commission one that does not. A Refurbishment Survey — the survey type historically known as 'type 3' before HSG264 retired the numeric labels in 2010 — is the intrusive survey commissioned before any work that will disturb the fabric of a pre-2000 building. It exists for one reason: to make sure that asbestos containing materials inside walls, above ceilings, under floor finishes and behind boxing-in are found and dealt with before a contractor's blade, hammer or drill discovers them. Get this survey wrong and a project loses weeks to mid-programme stops, contractor demobilisation, HSE notification and emergency licensed removal at three to five times the planned price. Get it right and the asbestos becomes a line item in the tender pack like any other. This guide explains scope, timing, cost and the recurring failure modes that cause refurbishment projects to derail.
What 'refurbishment survey' means under HSG264
HSG264 defines the refurbishment survey as the intrusive survey required where the building, or a defined part of it, is to be upgraded, refurbished or altered in a way that disturbs the fabric. Its purpose is to identify all ACMs that the planned works could reasonably disturb — not every ACM in the building. The scope is therefore defined by the works package, not by the building footprint. A refurbishment survey for a kitchen replacement opens up the kitchen, the floor below if pipes are being rerouted, and the riser the new feed will be taken from. A refurbishment survey for a full Cat A strip-out opens up everything within the demised area.
What this means
The survey scope is set by the works scope. Write the works scope clearly first — the surveyor cannot guess what your contractor will do.
When the law requires one
CAR 2012 regulation 5 prohibits any work liable to disturb asbestos without first identifying whether asbestos is present. CDM 2015 puts the duty on the client and the principal designer to provide pre-construction information that includes an asbestos refurbishment survey for any project on a pre-2000 building. In practice the duty is often delegated to the principal contractor, but the client cannot delegate the original obligation. The HSE's enforcement position has been consistent for over a decade: a contractor encountering asbestos because no refurbishment survey was commissioned is itself evidence of a regulatory failure by the client.
What this means
The client owns the duty. Delegating it to the contractor does not transfer the liability if something goes wrong.
What 'intrusive' looks like in practice
The surveyor will: lift carpets and vinyl, lift suspended ceiling tiles in full (not just look over the edge), drill exploratory holes through dry-lining to inspect studwork cavities, remove access panels, open boxing-in around pipework, lift loose floorboards, inspect inside risers and IT cabinets, and access loft and roof voids. On a kitchen survey the units are usually emptied and a section of plinth and back panel is removed. On a partition strip-out the surveyor confirms whether the partitions are AIB-lined by sampling at multiple points. Made-good reinstatement (filler, capping plaster, ceiling tile reseat) is usually included; full decorative reinstatement is not.
What this means
If the surveyor leaves the site without lifting anything, opening anything or drilling anything, you have not had a refurbishment survey. You have had a management survey wearing the wrong label.
Scope of works package — the document that drives everything
Every refurbishment survey should be commissioned against a written scope of works that lists the rooms affected, the elements being changed (ceilings, partitions, floor finishes, M&E first fix, decorations), and the depth of intervention (cosmetic, light refurb, full strip-out, structural). Without this document the surveyor is guessing. With it, the surveyor can plan intrusive openings, agree access with the occupier, and write a report that maps every finding directly to a works element. A properly scoped survey makes the contractor's tender pricing more accurate and protects everyone if a variation arises.
What this means
A one-page scope of works pinned to the survey instruction is the single most valuable piece of paper in the whole project file.
Vacating the area — when and why
Most refurbishment surveys require the area to be vacated for the duration of the works. This is not bureaucracy — it is because intrusive openings generate suspect dust that must be controlled, and because occupants and stored furniture get in the way of meaningful inspection. On occupied commercial buildings the survey often runs out of hours or at weekends, with the area returned to use by Monday morning. On domestic kitchens and bathrooms the survey is typically half a day with the occupier out. On NHS or school estates the survey is sequenced around half-term, school holiday or planned ward closure.
What this means
If the area cannot be vacated, the survey will be partial. Partial surveys are not compliant for the parts that were skipped.
Cost and timescales — 2026 UK figures
Domestic kitchen or bathroom refurbishment survey: £350–£650. Small commercial unit (single retail, single floor of 200–500 m²): £700–£1,800. Mid-size office or school block being stripped out (1,000–3,000 m²): £2,500–£6,500. Whole-building Cat A strip-out (5,000–10,000 m²): £6,500–£15,000+. Site time: half a day for a domestic kitchen; 1–2 days for a small commercial unit; 3–10 days for a school or mid-size office. Report turnaround 5–10 working days standard, 48 hours at express premium. Include sampling cost (£30–£60 per sample) and reinstatement budget in the brief.
- •Domestic kitchen / bathroom: £350–£650
- •Small commercial unit (200–500 m²): £700–£1,800
- •School or office (1,000–3,000 m²): £2,500–£6,500
- •Cat A strip-out (5,000–10,000 m²): £6,500–£15,000+
- •Sample analysis: £30–£60 per sample
- •Standard report turnaround: 5–10 working days
What this means
The refurbishment survey is almost always under 0.5% of project cost. Skimping on it is the worst possible place to save money on the programme.
Reading the report — what to look for
A compliant refurbishment survey report should give you, for every works element, either a sampled identification of any ACM present, a 'no asbestos detected' result, or an explicit caveat where the area could not be accessed and an assumption must be made. The report must include marked-up drawings showing every intrusive opening, photographs of every finding, UKAS sample certificates, and a recommended removal scope linked to the works package. Anything left as 'presumed' should be flagged as a residual risk for the contractor to manage, with the cost of confirming it during enabling works costed in.
What this means
Every ACM should be either sampled, presumed-and-flagged, or explicitly caveated. There is no fourth category — silence on an area means it was missed.
Found this guide useful?
Need refurbishment surveys surveyed or removed?
Same-day written quotes from senior, UKAS-accredited consultants. coverage across England and Wales, from Leeds southwards — no obligation.
Linking the survey to the removal tender
The output of the refurbishment survey should feed directly into a written asbestos removal specification that goes to three or four pre-qualified contractors. The specification names each item, the quantity, the regime (licensed, NNLW, non-licensed), the analyst arrangement, the disposal route and the reinstatement responsibility. Done this way, the removal package routinely prices 20–40% lower than the same scope handed to a single contractor as an informal walk-around. The survey on its own is the diagnostic; the specification is the lever that turns the diagnostic into a competitive tender.
What this means
The survey alone does not save you money — the specification and tender that follow it do. Plan for both.
Why projects discover asbestos mid-programme
The recurring causes are: client commissioned a management survey thinking it was the same thing; the refurbishment survey was scoped only to the obvious rooms and missed an adjacent riser or void the works actually entered; the survey was commissioned against drawings that the contractor then varied; the survey was done before a change of design that introduced new openings; or the building had a previous register that was relied on but never reinspected. Every one of these is avoidable, and the cost of avoiding it is a fraction of the cost of dealing with the consequences.
What this means
Most mid-programme asbestos discoveries are not bad luck — they are traceable to a specific failure in survey commissioning. Audit your own process before blaming the surveyor.
What happens if asbestos is found
Found ACMs are either removed under controlled conditions before the works start, encapsulated and worked around with a written method statement, or left in place with a permit-to-work regime. The choice is driven by the works package: anything in the path of the works is removed; anything adjacent but undisturbed can be encapsulated or managed. The removal is sequenced into the programme — typically as an enabling works package before the main contractor mobilises. Air clearance follows licensed work; reassurance air monitoring follows NNLW.
What this means
Finding asbestos is the survey doing its job. It is not a problem until you find it during the works rather than before them.
Surveyor competence and independence
BOHS P402 minimum, ideally P405. UKAS 17020 accredited surveying organisation. Independent of any removal contractor that may bid for the resulting works. Named lead surveyor in the proposal. £5m–£10m PI and £10m PL insurance. On larger or higher-risk projects (schools, hospitals, occupied commercial) ask for two recent references and a CV. The cost difference between a UKAS-accredited firm and a non-accredited one is usually £100–£300 on a small job and is one of the easiest false economies to avoid.
What this means
Independence and accreditation are not nice-to-haves on refurbishment surveys — they are the difference between a defensible report and a problem.
Frequently asked questions
Who is responsible for commissioning a refurbishment survey?
The client and principal designer under CDM 2015. In practice the duty is often delegated to the principal contractor, but the original liability remains with the client.
How long does a refurbishment survey take?
Half a day for a domestic kitchen, 1–2 days for a small commercial unit, 3–10 days for a school or mid-size office, 10–20+ days for a Cat A strip-out of a whole building.
What does it cost?
£350–£650 for a domestic kitchen or bathroom; £700–£1,800 for a small commercial unit; £2,500–£6,500 for a school or mid-size office; £6,500–£15,000+ for a whole-building strip-out.
Can a management survey be used instead?
No. A management survey is non-intrusive and assumes the building stays in occupied use. It does not look in the places a refurbishment will open up. Using one for refurbishment is a regulatory and a commercial failure.
Do I need one for a small domestic kitchen replacement?
If the property is pre-2000 and the works disturb the fabric (pipework rerouting, tile removal, partition changes, ceiling work), yes. Most domestic kitchen surveys are half a day and £350–£500.
Does the surveyor reinstate after intrusive openings?
Most surveyors make good with filler and capping plaster. Full decorative reinstatement (matched paint, retiling) is not included and should be budgeted separately.
Can the same firm do the survey and the removal?
Possible, but a conflict of interest risk. Best practice is to keep survey and removal separate on any significant project, so the removal scope can be tendered competitively.
What if my building was built after 2000?
A refurbishment survey is not legally required, but most clients still commission a documented inspection so the register and the tender pack carry a clean baseline.
What if asbestos is found mid-works despite a survey?
Stop the works in the affected area, isolate it, notify the principal contractor and dutyholder, and bring the surveyor back. Survey limitations and caveats should already have flagged the residual risk — work resumes once removal or encapsulation is complete.
Do I need to vacate the area for the survey?
Usually yes. Intrusive openings cannot be done meaningfully around occupied furniture and live use. Out-of-hours and weekend surveys are routine to minimise disruption.
How long is the report valid for?
The report is valid for the works package it was commissioned against. If the works change materially, the survey must be revisited. A refurbishment survey is not a perpetual register.
Speak to an independent senior consultant about your project
The UK's Independent Asbestos Consultancy. Evidence-based recommendations, UKAS-accredited surveyors, coverage across England and Wales, from Leeds southwards. Every enquiry is reviewed by a senior consultant — consultancy before sales, no obligation.
Read next
For this section- Demolition SurveysWhere the refurbishment survey ends and the demolition survey takes over.
- Management SurveysThe non-intrusive cousin — used for occupied buildings, not project works.
- Asbestos SamplingHow the bulk sampling that powers every refurbishment survey actually works.
- Asbestos Removal Costs in the UK (2026)Where the removal scope identified by the survey sits in the 2026 UK price map.